> Photo Gallery    > Press Releases

WIRELESS BROADBAND Latest News

Moving through the Phases

[05-14-2012] Big River Broadband has good news on the development of the Broadband build out! We are in the process of testing services right now with 10 tower sites that are in the final phases. Five of these sites are in Cape County, three are in St. Francois County, and two are in Ste. Geneveive County! We are currently doing some select testing and research on the network as we are checking service strength, quality, reliability, and making sure we can get every bit of upload and download possible. Towers are continuing to progress through the several installation and alignment processes as well. Six tower sites are working on their backhaul and radio installation at this time; four are in St. Francois County, one is in Madison County, and one is in Ste. Genevieve County. With these six in their installation process and finishing up, we have another four that are scheduled to immediately follow. They are located in Bollinger and Ste. Genevieve Counties.

Six more towers are in their construction phase and are progressing through it with this great weather we have been having. They are located in Washington County, Perry County, Ste. Genevieve, Cape and St. Francois Counties. We have eight towers in construction contract negotiations, with a majority in Bollinger County and Perry County. Two are in Madison and St. Francois Counties also. Eight more tower sites are completing environmental and geotechnical analysis and reporting, and they are located in Bollinger, Washington, Ste. Geneveive, and St. Francois Counties. Lastly, we currently have four tower sites obtaining their preliminary microwave analysis and are looking to move forward into the next phases. These are in Cape, Madison, and Washington County.

With the development of these towers moving towards more and more being tested and turned on, we have been able to expand with two new hires on the technical side of the broadband development. Another installer and a network operations specialist have joined the Big River Broadband team to help manage the system and run the installation and delivery of Broadband to our customers. We have begun the testing process with receivers across the area to try out the towers service and are daily collecting information on what is working well, what needs improvement, and how we can streamline and develop the sales process as we look forward to launching to the public as soon as possible! This is big and getting closer day by day! Stay up to date at www.bigriverbroadband.com, like us on Facebook, and follow us on Twitter @BigRiverCares for all your Big River Broadband information!


Updates and Technical Details

[04-18-2012] More progression with the towers! Lots of work on the technical side has been going on, and we’re going to explain as much as we can for what that means at the end of these updates! For the Co-location tower sites, those we did not have to build from the ground up, AWS and Microwave radio equipment has been installed on 9 towers: five in Cape County, one in Ste. Genevieve County, three in St. Francois County. AWS equipment has been installed with the Microwave radio equipment scheduled for this week on an additional 3 towers: one in St. Francois County, one in Madison County, and one in Bollinger County. We are excited to say that with these progressions, we have now been starting to pass data back and forth from some of the towers to our core network, clearly the most important technology update as this means towers are now beginning to be improved and tested for quality, strength and signal.

On our New Build/Raw Land towers, four have had AWS and Microwave radio equipment installed and six more have the AWS installed with the Microwave installation scheduled for this week and next week. Once this is all installed and tested, we will begin to be able to send data back and forth from them to the core network, a rigorous process, but one that we hope will go smoothly as we get more experienced with the process and can streamline the release. Please remember this is an entirely new network and experience and we are going to deliver the best possible product to the customer, which takes time and finesse! Being ahead of schedule to this point has been a tremendous boost and we are excited to continue to roll this out!

For our next set of Raw Land Builds, we are finishing construction company tower build proposals, contracts, and negotiations, as they have all moved into the next phase after undergoing the extensive environmental and geotechnical testing and analysis. There are fourteen towers in this group that we plan to continue with construction as soon as possible. There are two in Cape County, four in Perry County, two in St. Francois County, one in Ste. Genevieve County, one in Washington County, three in Bollinger County, and one in Madison County. Eight more towers are undergoing and finishing their environmental and geotechnical testing and analysis. Three are in Bollinger County, two in St. Francois County, one in Ste. Genevieve County, and two in Washington County. We have a final four towers with a completed survey and are scheduled to undergo this testing across the region: one in Cape, one in Madison, and two in Washington.

A brief explanation of each of the technical processes is listed below. This is to give a better understanding of what goes into each installation of equipment and what some of the many testing requirements we have to follow.

AWS Installation- Advance Wireless Spectrum or simply AWS pertains to the frequency we use to deliver broadband service and the installation of this technology consists of mounting antennas, radios and cabling on our towers and then tying that back into our core voice and data network over microwave or fiber.

Microwave/Backhaul Installation- In order to deliver bandwidth to our tower sites we need to have a transmission medium. This medium will be either licensed microwave or terrestrial connections to the tower sites.  In the case of microwave, our installation consists of many steps. We perform several studies to make sure the topology between any two points is suitable for a microwave link.  Once we determine the length of the “shot” and the line of sight is available we will complete engineering and order towers to achieve the desired link parameters.  Because we use licensed microwave frequencies we must coordinate with the FCC and be granted a license that specifies the frequencies we’re using, the height of the microwave antennas and the land coordinates for the towers onto which the gear will be placed.

Alignment Processes- Along with clear line-of-sight, aligning/pathing a link involves several other design considerations. We need to consider free space loss (how much signal weakens over a given distance), antenna gain (how much an antenna boosts the RF signal), transmit power (how much RF power is actually output) and several other design considerations.  Again, all of the parameters that go into the design and alighment of the link will be submitted to the FCC and keep in their database.
Once the link is in place a substantial amount of integration and commissioning tests are run on the links.

Testing- Based upon results of testing at each of these different phases of installation, progressing through the process could take as little as a few weeks to a few months. We undergo call testing, bit rate testing, transmission and reception testing, with strength and quality maximized at each level, and more.

This is a very general and simplified description of the technology aspect of the tower buildouts, but we hope to assist in any clarification you might need in understanding the updates and process of delivering you the Big River Broadband 4G LTE Network!


Big River Broadband Event a Success

[04-11-2012] Monday and Tuesday, April 9th and 10th, proved to be two very BIG days in Big River Broadband’s build-out process of 4G LTE broadband internet. Our partner, Alcatel-Lucent, was in town at the new Broadband Headquarters Open House to deliver a truly unique and big experience to the public by demonstrating the power of 4G LTE technology in their mobile Executive Briefing Center. Hundreds showed up for the two day event to participate in sessions put on by the Alcatel Lucent and the Big River crew to gain information about what Big River Broadband is deploying to the 7 county region. With an address from Governor Jay Nixon to the crowd Monday night, entertainment, food and drink, these past few days have been great fun and excitement for the area. Downtown Farmington was host to a large group of visitors and a good time was had by all!

You can view pictures from the two-day event below:

Day 1

 

Day 2


News coverage and articles of the Governor's visit and Big River's efforts can be viewed below:

The Southeast Missourian

Daily Journal Online

MoBroadbandNow

Missouri News

KFVS12

MyMoInfo


The Big River Experience

[04-04-2012] Next Monday, April 9th and Tuesday, April 10th, we will be hosting the Big River Broadband Experience in Farmington, to celebrate the opening of our new Farmington headquarters.  This two day event will include demonstrations of the opportunities and possibilities our 4G LTE Broadband internet will provide the seven county region we’re building in.

People attending the event are going to be able to experience firsthand applications, such as:  real scenarios, business to business applications, live cast, public safety demonstration and connected classroom, just to name a few.

Daily one-hour sessions ARE invitation only, but from 4:30 pm – 6:30 pm each evening  there will be an open house with food and music that will be open to the public.  On Monday, April 9th at 4:30 pm, Governor Jay Nixon and his staff will be in attendance.
If you are interested in going to the Big River Broadband Experience, and would like to reserve a seat, please contact Dana Hukel at BOLD Marketing at 573-803-0676 or dana@getboldmarketing.com.  Seating is limited and filling up fast.  So please don’t wait until last minute!


Status of Tower Construction Sites

[03-28-2012] We have lots of updates on the construction of towers across the seven county region. For the first group of 10 raw land construction towers, we have moved into completing most equipment cabinet installations and construction. All of them are completely constructed and erect. One has complete radio connectivity and microwave dishes have been installed, and this one is in Ste. Genevieve. Five sites have radio cabinets installed and connected to the Remote Radio Head with microwave connection in process this week, three of these are in Ste. Genevieve and two in St. Francois. The other four sites have the Remote Radio Head connectivity and microwave installation scheduled for these next two weeks. Two of these are in St. Francois, one is in Perry, and one is in Ste. Genevieve. These are the updates for the first raw land or “new build” as we also call them, towers.

For the first round of our Co-located towers, one site is with cabinet and Remote Radio Head connectivity, microwave installation and alignment and completely integrated with testing, and that is in Cape Girardeau. Three sites have this integrated testing going on starting this week, and they are also in Cape Girardeau. One site in Ste. Genevieve is just as far and has its integrated testing scheduled for next week. There are three towers in St. Francois County that are about to be ready to schedule the testing with the system, these dates are being scheduled for within the upcoming month. Equipment installation is being scheduled this week for one tower in Madison and one tower in Bollinger counties.

Current construction bidding is occurring on five towers, two in Cape, one in Perry, one in St. Francois, and one in Ste. Genevieve. Once this is complete, we can move them into the construction phase. 

We are waiting on the government to approve eight towers we have submitted to them. Once we get RUS Environmental approval, we will start the contract bidding and construction. Three of these are in Perry County, three are in Bollinger County, one is in Madison County, and one is in St. Francois County. We are anxiously awaiting their approval to get these towers underway!

We have eight towers finishing the engineering phase which includes completed environmental analysis and geotechnical boring, which requires taking a thorough sample of the land to be tested for quality ground surveying and takes three weeks to undergo testing. This process is underway at three tower sites in Bollinger County, two tower sites in St. Francois, one in Ste. Genevieve, and two in Washington County. We are scheduling site surveys on four towers for the next few weeks, one in Cape, one in Madison, and two in Washington county.
Though the process is arduous and it feels like it has been an eternity since the project was began, we are actually only EIGHT months into the projected TWENTY month project. This means, that within 40% of the time frame we have to complete this project, we have already begun and progressed rapidly through miles of paperwork and research, submissions and approvals, ground breakings and now onto tower completions. We know the frustration and demand for the product as we work daily to answer questions, make decisions, and progress towards our final goal of providing high quality broadband internet to those never adequately served before. Your patience and support are greatly appreciated as we continue to bring jobs to the area and take this part of southeastern Missouri into the modern era of internet!


Build-Out Status

[03-13-2012] Here are the latest updates on the Broadband build-out tower construction process: Of the eleven co-location towers, nine have radio cabinets now set that will have testing starting next week. After this testing is completed, microwave installation will follow within the next two to three weeks. One is in Bollinger, five in Cape County, three in St. Francois County, one in Madison County, and one in Ste. Genevieve County. For ten of the New Build towers, eight are erected with the radio cabinets set at the sites, testing will begin next week and microwave installation over the next two to three weeks. This includes five in Ste. Genevieve, three in St. Francois, one partially erected in St. Francois and one ready to be erected in Perry County.

Here is a bit of a breakdown on what phase some of the remaining towers are in: Construction negotiation is currently taking place on six towers, two in Cape County, one in St. Francois, one in Ste. Genevieve, one in Perry, and one in Washington. There are 8 towers awaiting final environmental approval; three in Perry, three in Bollinger, one in St. Francois, and one in Madison County. Towers undergoing the environmental and geotechnical testing include eight, with locations across Washington, Bollinger, St. Francois, and Ste. Genevieve, and four more towers have scheduled site surveys within Washington, Cape, and Madison Counties.

As with any new project, especially one as large as this Broadband initiative, there is a speed curve that develops once you’ve smoothed out the steps necessary to take as you move along. The more times you repeat the process, the faster it goes and the amount of time a tower takes to go from beginning to end gets faster because the process is more regular. As our beginning towers are finishing and getting ready to be deployed, we are able to pick up speed (as much as we can) in moving along with towers earlier on in the process because we know what to expect and do. This is one of the first of its kind in its development, and coming from a small CLEC, we hope that all appreciate and understand the work going in to bringing the best of services possible to the currently underserved. This is BIG, for us and you, and Big River Broadband won’t stop until it’s complete!


Construction Upgrades Continue

[02-23-2012] This week we have 5 equipment cabinets being installed at collocation towers; meaning we are installing the electronics to connect AWS antennas with our core network. Four of these towers are within Cape County and one is within Ste. Genevieve County. The remaining five cabinets for our 5 other co-location towers will be installed over the next two weeks. This includes one site in Bollinger County, one in Madison County, and three in St. Francois County. After this, the Microwave installation will follow for all ten collocated towers. 

For ten of our raw-land construction towers, equipment cabinets are set to be installed on 6 of the towers. One is in Ste. Genevieve County, two are in St. Francois County, and 3 are in Ste. Genevieve County. Four of the towers in construction are currently with foundation and in the process of being erected. These include one in both Perry and Ste. Genevieve County and two in St. Francois County.

Six other new towers that are ready for construction are spread across the region with 2 in Cape, 1 in Perry, 1 in St. Francois, 1 in Ste. Genevieve, and 1 in Washington County. 8 towers are waiting for final Environmental approval, the final step before construction. There are 3 towers in Bollinger County, 1 in Madison County, 3 in Perry County, and 1 in St. Francois County.

In total, 13 towers are in the first three phases, including finalizing tower height, beginning environmental and geotechnical testing, and site surveys. Four are in Bollinger County, 2 are in St. Francois County, 1 is in Ste. Genevieve County, 4 are in Washington County, and 1 is in Madison County. These progress quickly though the phases once contracts and walk-throughs are completed. We are taking no days off in this process and are actively working to provide you with the best in high speed Broadband Internet!


Towers Being Updated

[02-13-2012] Towers are well on their way and progressing through the stages towards completion rather quickly. We have eleven co-location towers that are ready for the equipment cabinet and microwave installation. There is on in Bollinger, five in Cape County, one in Madison, one in Ste. Genevieve, and three in St. Francois.

We have New Build towers that are also completely erected and ready for the equipment cabinet and microwave installation. These five towers are in St. Francois County and Ste. Genevieve.  Five more towers are in construction. One is in Perry County, three are in St. Francois County, and one is in Ste. Genevieve County.

There are six towers with finalized drawings and are ready to begin construction. Two of them are in Cape Girardeau, one is in Perry County, one is in St. Francois County, one in Ste. Genevieve County, and one in Washington County.  Eight more towers are works in progress with the construction drawings. Bollinger has three towers, Madison has one tower, Perry has three towers, and St.  Francois has one tower.

There are fourteen towers in the pre-engineering process. These towers are located across the area, with three in Bollinger, two in Cape County, one in Madison, three in St. Francois, one in Ste. Genevieve and four in Washington.

While the towers are being updated, work continues to prepare our new headquarters. Here are a couple of shots that we grabbed of our technicians pulling cable through the ceiling of the office:


We are moving along in the project and very excited to bring the Broadband network to everyone! THIS IS BIG!


Command Center

[01-26-2012] Our Big River Broadband office in Farmington, MO will be the main headquarters for Big River Broadband. Also located in Farmington is our warehouse that is serving as the main staging area for the tower builds across the entire build-out region. Below, you can take a sneak-peek at our main headquarters.


 


Towers being Built

[01-19-2012] Work continues on tower construction. If you see heavy equipment moving through your area, it might be us. Check out the pictures below to see the tower construction process.


Behind the Curtain

[01-17-2012] Here is a behind-the-scenes look at some of our co-located tower equipment. We didn't let a little bit of snowfall keep us from moving forward with our tower builds. These sites are in Cape Girardeau, Ste. Genevieve and Bollinger Counties.


THIS IS BIG Video Contest!

[01-09-2012] Big River Broadband is excited to announce a Video Contest where you can win $2,500! Big River is hosting a "THIS IS BIG" Video Competition in which we want you to show us what "THIS IS BIG" means to you! In a 1 minute or less video, show us how you think "THIS IS BIG" and upload it to your website to enter to win $2500! This contest begins on January 15th and goes through March 30th. Visit our website at www.bigriverbroadband.com/contest for complete rules. The contestant with the most votes will win!



New Year Updates

[01-06-2012] Great news for the progression of the tower construction within the region! Construction improvement has been made to the towers and we’re looking to be right on schedule. For the eleven co-location towers that are under construction - tower antennas and cabling have been hung; the pads for equipment, ground ring and power have all been installed. The next steps for these towers in our move towards completion and going live are to set the cabinets and install the microwave dishes. These sites are across the area, one within Bollinger County, five in Cape Girardeau, one in Madison, one in Ste. Genevieve and three in St. Francois County.

For our New Build towers that are currently under construction, we have 8 around the region actively being processed. Four of these sites are in Ste. Genevieve County in which the towers are erected, with antennas hung on two of them and the other two beginning to stack the towers. For these four, the next steps include installing power, cabinets, and microwave dishes. The three sites in St. Francois County are also underway. One of the towers is erect and is ready to have power, cabinets, and microwave dishes installed while the other two are undergoing foundation preparation, site clearing and ground excavation. The tower site in Perry County that is currently under construction is working on access and foundation preparation, including finalizing access from the roads to the site with the city and beginning excavation and foundation pouring.

The next round of sixteen sites that are in the engineering stages are also spread across the region. Three of the sites in Bollinger County are finalizing tower and compound drawings. The two sites in Cape, two sites in Ste. Genevieve, and two sites in Washington Counties are also finalizing tower and compound drawings. One site in Madison County, four sites in Perry and three sites in St. Francois are finalizing geotechnical reports and tower and compound drawings.

Lastly, pre-engineering site surveys and analysis are occurring on ten more areas within the region and are distributed as such: Bollinger - 3 sites, Cape Girardeau - 1 site, Ste. Genevieve - 1 site, St. Francois - 3 sites, and Washington - 2 sites.

Big River Broadband’s corporate offices are also nearing completion. You can view pictures of the progress below:

For more direct notifications and information to be sent to you as soon as a tower in your region is at Go-Live status, sign up under our Notify Me section on www.bigriverbroadband.com and follow us on Twitter or our Facebook pages!



NEWS ARCHIVES

 

inConnect | Residential Telephone | Business Telephone
Residential Internet
| Business Internet | Wholesale | Contact Us | About Us
Privacy Policy
| Terms & Conditions | Wireless Broadband Update
All Content © 2011, Big River Telephone | All Rights Reserved
Big River Telephone
24 South Minnesota Street | Cape Girardeau, MO 63702-1608
LOCAL 573-651-3373 | TOLL FREE 1-855-BIG RIVER (1-855-244-7483)